1) Download the Contractors FM Guide (PDF)

  1. Open the link provided to access the Contractors FM guide.

  2. Click Download (or View / Download PDF, depending on your browser).

  3. Save the file somewhere easy to find (e.g., Downloads or a shared folder)


 

Submitting a Quote

  1. Log in to Contractors FM.

  2. Go to the relevant Quote Request (this is usually accessed from your list of open quote requests).

  3. Open the quote request and review:

    • Work description

    • Site / address details

    • Required dates / deadlines

    • Any notes or attachments

  4. Select Submit Quote (or the equivalent action button).

  5. Enter quote details:

    • Labour / materials breakdown (if applicable)

    • Total cost

    • Proposed start and completion dates

    • Any assumptions or exclusions

  6. Attach supporting documents if required (e.g., itemised quote, scope notes).

  7. Click Submit to send the quote back through the system.

✅ Result: The quote is submitted and visible to the FM team for review/approval.

Accepting Works (Workorders)

  1. Log in to Contractors FM.

  2. Navigate to Workorders (or Jobs / Workorders Issued).

  3. Open the workorder you want to accept.

  4. Review the workorder details carefully:

    • Scope of works

    • Site details and access notes

    • Required SLA / due date

    • Purchase order reference (if shown)

    • Attached documents

  5. Click Accept Works (or Accept Workorder).

  6. Confirm acceptance when prompted.

✅ Result: The job moves into an “accepted / in progress” workflow and the FM team can track progress.


Updating Workorder Status

Keeping statuses up to date helps prevent delays and avoids invoice/payment issues later.

  1. Log in to Contractors FM.

  2. Open Workorders and select the relevant workorder.

  3. Find the Status section (or Update Status button).

  4. Choose the appropriate status, for example:

    • Accepted

    • Scheduled

    • On Site / In Progress

    • Works Completed

    • On Hold / Awaiting Parts

    • Unable to Access

  5. Add notes where needed (highly recommended), e.g.:

    • What was done today

    • What’s outstanding

    • Any access issues / tenant contact attempts

  6. Save / Submit the status update.

✅ Result: The FM team sees live progress and can respond quickly if anything is blocked.


Uploading Invoices for Payment Against Workorders

To avoid payment delays, make sure your invoice matches the workorder reference and totals.

  1. Log in to Contractors FM.

  2. Go to Workorders and open the completed workorder.

  3. Confirm the status is set to Works Completed (or the required completion status).

  4. Locate Invoices (or Upload Invoice / Submit Invoice for Payment).

  5. Upload the invoice PDF (and any required supporting documents).

  6. Enter invoice details if prompted:

    • Invoice number

    • Invoice date

    • Amount (ensure it matches approved quote/workorder value)

    • VAT (if applicable)

  7. Confirm the invoice is being submitted against the correct workorder.

  8. Submit.

✅ Result: The invoice is logged against the workorder and enters the payment approval process.


Suggested Admin Setup (Attach the PDF Guide to Quotes & Workorders)

Your FM Administrator can attach the PDF guide to each quote and workorder issued by uploading the document to Agency Communication.

Steps (FM Administrator)

  1. In FM, go to: Administration

  2. Select: Agency Communication

  3. Click Upload (or Add Document)

  4. Upload the Contractors FM guide PDF

  5. Save / Publish (depending on your system prompts)

✅ Result: The guide can be included/attached on outgoing Quotes and Workorders, so contractors always receive the instructions.

 

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article